PROJECT AUTHORIZATION |
PACKET ID: N/A |
CONTRACT ID |
EMARS PROGRAM CODE |
AUTHORIZATION NO: |
|
|
69777 |
6 |
It is hereby ordered that the project herein described be undertaken and accomplished within the funding level authorized. |
PROJECT ID |
PROJECT ID NUMBER |
FEDERAL PROJECT NUMBER |
6 YR PLAN ITEM NUMBER |
6 YR PLAN ITEM PARENT NUMBER |
|
059 0536 000-002 008 0536 014-015 |
STP 8206 005
|
06-00162 |
6-.- |
PROJECT TYPE |
PROJECT LENGTH |
NUMBER OF BRIDGES |
SYSTEMS |
RECONST W/ADD LNS |
4.5 MI |
|
|
PROJECT PHASE
&
RESPONSIBILITY |
PLANNING |
DESIGN |
RIGHT OF WAY |
UTILITIES |
|
DOH |
|
|
CONSTRUCTION |
TITLE DEEDED TO: |
MAINTENANCE |
OTHER |
|
|
|
|
FUNDING & TIME
ACCOUNTABILITY |
PARTICIPATING AGENCIES |
FEDERAL |
FHWA |
STATE |
DOH |
LOCAL |
|
OTHER |
|
REQUESTED FUNDS FOR THIS AUTHORIZATION
ITEM NUMBER |
PHASE |
FUND |
PROGRAM |
FEDERAL FISCAL YEAR |
STATE FISCAL YEAR
|
FEDERAL APPR
CODE |
CURRENT FUNDING REQUEST |
6-162.2 |
R |
1200 |
FD52 |
2017 |
2018 |
Z231 |
$3,500,000.00 |
CURRENT FUNDING REQUEST TOTAL: $3,500,000.00 |
AUTHORIZATION SUMMARY FOR THIS 10-1 SERIES |
PHASE |
TOTAL AUTHORIZATION TO DATE (INCL. CURRENT REQUEST) |
PLANNING |
$0.00 |
DESIGN |
$5,552,000.00 |
UTILITIES |
$0.00 |
R/W |
$3,750,000.00 |
CONSTRUCTION |
$0.00 |
NON-HIGHWAYS |
$0.00 |
|
Total: $9,302,000.00 |
THIS AUTHORIZATION PROVIDES INITIAL R/W FUNDS FOR SYP ITEM # 6-162.20 AS IDENTIFIED IN THE '16 SYP. TJ |
|
Project Approval Recommended By:
PCL 9/8/2017 |
Signed and Approved by:
MB 9/12/2017 |
ITEM NO. |
COUNTY |
DIST |
FACILITY NAME
|
ROUTE |
LENGTH |
06-00162.20 |
KENTON
BOONE
|
6 |
MOUNT ZION RD BRISTOW RD INDEP |
KY 536 |
4.5 MI |
RECONSTRUCT KY 536 FROM THE EAST END OF THE NS RAILROAD BRIDGE (B91)(MP 14.363 IN BOONE) TO KY 1303 (MP 1.061). (16CCN) |